Yellow dump truck loading minerals copper, silver, gold, and other  at mining quarry.

Mining operation and processing at BUMBAT AND KHALZAN open pit mine

6 million m3 overburden and 315 thousands m3 sand extraction work was carried out at Bumbatand Khalzan open pit mine located in Zaamar soum of Tuv province.
8

Mining operation and processing at DORGONOT open pit mine

5 million m3 overburden and 300 thousands m3 sand extraction work was carried out at Dorgonot open pit mine located in Dashinchilen soum of Bulgan province.
10

Mining exploration and operation at Ovoot Tolgoi coal mine

Ovoot Tolgoi coal mine is located in Gurvan Tes soum of Umnugovi province, owned by SGS LLC.

Mongolia's vast reserves of high-quality coal, combined with its close proximity to country, the world's largest consumer of coal, and high demand Asian markets - make Mongolia a growing strategic player in the global coal market.
gold_mining

Mineral exploration work at Naran Gol open pit mine

In total 3500 m2 of land exploration work was completed at Naran gol open pit mine located in Bayangol soum of Selenge province.

Mining operation and processing at NARAN GOL open pit mine

15 million m3 overburden and 400 thousands m3 sand extraction work was carried out at Naran Gol open pit mine located in Bayangol soum of Selenge province.
Тайширын хайгуулын

Mineral exploration work at Taishir open pit mine

In total 26267.9 hectares of land, exploration work was completed at Taishir open pit mine located in Taishir soum of Govi-Altai province.
13

Additional Mineral exploration work at Urt Bulag open pit mine

In total 878.8 m2 of land, an additional exploration work was completed at Urt Bulag open pit mine located in Bayangol soum of Selenge province.
11

Mineral exploration work at Ovoot Tolgoi open pit mine

In total 165.52 hectares of land, exploration and geological report’s works are being carried out at Ovoot Tolgoi open pit mine located in Bayangol soum of Selenge province.

Railroad construction work of Zuunbayan-Khangi 226km

Construction work of railroad base structure between PK164+000 and PK173+300 was completed on the project of Zuunbayan-Khangi.
olloo_mn_1456285494_zamtomor-810x484

Railroad construction work of Bogdkhan 144.9km

We were chosen as a Subcontractor of Construction work of railroad base structure on the project of Bogdkhan Railroad from the over 60 entities by tender announcer.

Project implementation time is 4 years and Construction work of railroad base structure between PK1244+80 and PK1270+20 was completed.
exec

Property Management

Executive Excellence LLC is representing our entry to the real estate management sector by providing service of comfortable, safe workplace, advanced technology and consulting service in this era of rapidly growing competition.
15

Mining operation and processing at TSAGAAN CHULUUT open pit mine

4.3 million m3 overburden and sand extraction work was carried out at Tsagaan chuluut open pit mine located in Zaamar soum of Tuv province.
1111111

Mining operation and processing at BAGA HAILAAST open pit mine

8.9 million m3 overburden and sand extraction work was carried out at Baga hailaast open pit mine located in Zaamar soum of Tuv province and Rehabilitation work fully completed.
14

Mining operation and processing at AR NAIMGAN & UVUR NAIMGAN open pit mine

6.8 million m3 overburden and sand extraction work was carried out at Ar naimgan & Uvur naimgan open pit mine located in Zaamar soum of Tuv province and Rehabilitation work fully completed.